Laporan Bulan Ini


STATUS PEMANTAUAN PROJEK (KERJA FIZIKAL DI TAPAK)

 

KERJA ANTI TERMITE

BANGUNAN UTAMA

KERJA PEMASANGAN PAIP UNTUK ANTI TERMITE DI ZON 2 SEDANG DIJALANKAN.

 

KERJA RASUK TANAH

KERJA-KERJA KONKRIT RASUK TANAH UNTUK ZON 2 TELAH DISIAPKAN KESEMUANYA PADA 09.09.2015.

 

PAPAK LANTAI TANAH

ZON 1, AKTIVITI: SIAP KONKRIT KESEMUA PAPAK LANTAI TANAH PADA 14.09.2015 (100%)

ZON 2, AKTIVITI: KONKRIT SEHINGGA GRID LINE D-J/ 9-13.5, D-H1/ 13.5-16 & D-H/ 16-17. (54%)

ZON 3, AKTIVITI: SIAP KONKRIT KESEMUA PAPAK LANTAI TANAH PADA 10.09.2015 (100%)

 

TIANG

ZON 1, AKTIVITI: KONKRIT 68 NOS DARIPADA KESELURUHAN 122 NOS (69%)

ZON 2, AKTIVITI: KONKRIT 10 NOS DARIPADA KESELURUHAN 96 NOS (10%)

ZON 3, AKTIVITI: KONKRIT 66 NOS DARIPADA KESELURUHAN 78 NOS (85%)

 

CORBEL (LEVEL 2)

ZON 1, Aktiviti: KONKRIT 1 NOS DI GRID LINE M/9 (2%)

ZON 3, Aktiviti: KONKRIT 6 NOS DI GRID LINE M/ 10-12 & R/ 16-18 (27%)

 

NIB BEAM (LEVEL 2)

KERJA-KERJA PEMASANGAN KOTAK BENTUK SEDANG DILAKUKAN DI GRID LINE 3/ F-Q & 4/ G-M UNTUK ZON 1.

KERJA-KERJA PEMASANGAN KOTAK BENTUK SEDANG DILAKUKAN DI GRID LINE 10/ M-R, 11/ M-R, 12/ M-R & 13/ M-R UNTUK ZON 3.

 

HOUSEMEN QUARTERS DAN NURSES HOSTEL

KERJA TETOPI CERUCUK HOUSEMEN QUARTERS & NURSES HOSTEL

SEHINGGA 27.09.2015

ZON HOUSEMEN QUARTERS (31 nos), PENGOREKAN (31 nos), KONKRIT TETOPI CERUCUK (31 nos) DAN PERATUS TETOPI CERUCUK YANG SIAP DIKONKRIT (100%)

ZON HOUSEMEN QUARTERS (33 nos), PENGOREKAN (33 nos), KONKRIT TETOPI CERUCUK (32 nos) DAN PERATUS TETOPI CERUCUK YANG SIAP DIKONKRIT (97%)

 

RASUK TANAH

HOUSEMEN QUARTERS

KERJA-KERJA KONKRIT RASUK TANAH DI GRID LINE D-H/ 1-4.

KERJA-KERJA PEMASANGAN KOTAK BENTUK DAN BESI TETULANG RASUK TANAH SEDANG DILAKUKAN.

NURSES HOSTEL

KERJA-KERJA PEMASANGAN KOTAK BENTUK DAN BESI TETULANG RASUK TANAH SEDANG DILAKUKAN.

 

KERJA-KERJA TETOPI CERUCUK

BLOK M&E
SEHINGGA 27.09.2015

BANGUNAN BLOK M&E (63 nos), PENGOREKAN (43 nos), KONKRIT TETOPI CERUCUK (38 nos) DAN PERATUS TETOPI CERUCUK YANG SIAP DIKONKRIT (60%)

 

KERJA-KERJA STUMP

BLOK M&E
SEHINGGA 27.09.2015

BANGUNAN BLOK M&E (63 nos), KONKRIT STUMP (38 nos) DAN PERATUS STUMP YANG SIAP DIKONKRIT (60 %)

 

BALAI PELAWAT

PAIP SANITARY
KERJA-KERJA PEMASANGAN PAIP SANITARY UNTUK BALAI PELAWAT TELAH DILAKUKAN.

BESI
KERJA-KERJA PEMASANGAN BESI BAGI ASAS RAKIT UNTUK BALAI PELAWAT TELAH DILAKUKAN.

 

BLOK TADIKA

PAIP SANITARY
KERJA-KERJA PEMASANGAN PAIP SANITARY UNTUK BLOK TADIKA TELAH DILAKUKAN.

 

AC/DC

KERJA AC/DC – JALAN SUSUR KELUAR- MASUK

KERJA PENGOREKKAN TANAH KE ARAS SUB GRADE TELAH DILAKUKAN.

KERJA MENGHAMPAR LAPISAN PASIR (SUB BASE) TELAH SIAP DILAKUKAN.

KERJA MENGHAMPAR LAPISAN CRUSHER RUN (ROAD BASE) TELAH SIAP DILAKUKAN.

Perancangan Bulan Hadapan


KERJA FIZIKAL

KERJA ANTI TERMITE DAN KERJA PAPAK LANTAI DAN KERJA-KERJA UNDERGROUND SERVICES BAGI M&E

PENYIAPAN BAKI KERJA PEMASANGAN PAIP UNTUK ANTI TERMITE UNTUK ZON 2 (TARGET SIAP DARI 60-100%).

ZON 2, TARGET SIAP BAGI KERJA PAPAK LANTAI TANAH (50-100 %) DAN TARGET SIAP BAGI KERJA M&E (75-100%)

 

TIANG

PENYIAPAN BAKI KERJA-KERJA PEMBINAAN TIANG UNTUK ZON 1. (TARGET SIAP DARI 68%-100%).

PENYIAPAN KERJA-KERJA PEMBINAAN TIANG BAGI ZON 2 (TARGET SIAP 100%)

PENYIAPAN BAKI KERJA-KERJA PEMBINAAN TIANG UNTUK ZON 3. (TARGET SIAP DARI 84%-100%).

 

CORBEL & NIB BEAM LEVEL 2

PENYIAPAN BAKI KERJA PEMBINAAN CORBEL & NIB BEAM LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 100%).

 

IBS BEAM LEVEL 2

PENYIAPAN PEMASANGAN IBS BEAM BAGI LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 100%).

PEMASANGAN IBS BEAM LEVEL 2 UNTUK ZON 2 (TARGET SIAP 50%).

 

BEAM CAST IN SITU LEVEL 2

PENYIAPAN PEMBINAAN BEAM CAST IN SITU BAGI LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 100%).

PEMASANGAN BEAM CAST IN SITU BAGI LEVEL 2 UNTUK ZON 2 (TARGET SIAP 50%).

 

BEAM CAST IN SITU LEVEL 2

PENYIAPAN PEMBINAAN BEAM CAST IN SITU BAGI LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 100%).

PEMASANGAN BEAM CAST IN SITU BAGI LEVEL 2 UNTUK ZON 2 (TARGET SIAP 50%).

 

TIANG LEVEL 2

KERJA-KERJA PEMBINAAN TIANG LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 50%).

 

NURSES HOSTEL & HOUSEMEN QUARTERS

RASUK TANAH

PENYIAPAN BAKI KERJA PEMBINAAN RASUK TANAH UNTUK NURSES HOSTEL (TARGET SIAP DARI 30%-100%).

PENYIAPAN BAKI KERJA PEMBINAAN RASUK TANAH UNTUK HOUSEMEN QUARTERS (TARGET SIAP DARI 60%-100%).

 

NURSES HOSTEL & HOUSEMEN QUARTERS

PAPAK LANTAI TANAH

KERJA-KERJA PEMBINAAN PAPAK LANTAI TANAH UNTUK NURSES HOSTEL (TARGET SIAP 100%).

KERJA-KERJA PEMBINAAN PAPAK LANTAI TANAH UNTUK HOUSEMEN QUARTERS (TARGET SIAP 100%).

 

BLOK M&E

TETOPI CERUCUK

PENYIAPAN KERJA-KERJA PEMBINAAN TETOPI CERUCUK UNTUK BLOK M&E (TARGET SIAP DARI 60%-100%).

RASUK TANAH

KERJA-KERJA PEMBINAAN RASUK TANAH UNTUK BLOK M&E (TARGET SIAP 50%).

 

BLOK BALAI PELAWAT & TADIKA

KERJA ASAS TAPAK

KERJA-KERJA PEMBINAAN ASAS TAPAK BLOK BALAI PELAWAT. TARGET SIAP DARI 75%-100%.

KERJA-KERJA PEMBINAAN ASAS TAPAK BLOK TADIKA. TARGET SIAP DARI 30%-100%.

 
 

KERJA FIZIKAL (INFRA)

KERJA AC/DC

KERJA MENGHAMPAR LAPISAN PREMIX BINDER COARSE. TARGET SIAP 100%.

KERJA MEMBINA LONGKANG DAN PEMBENTUNG. TARGET SIAP 100%.

 

KERJA FIZIKAL (INFRA)

KERJA LINK BRIDGE

KERJA PILING. TARGET SIAP 100%

KERJA PENGHANTARAN BOX CULVERT KE TAPAK. TARGET SIAP 100%.

KERJA PEMASANGAN BOX CULVERT. TARGET SIAP 50%.

 

KERJA FIZIKAL (INFRA)

(KERJA MAIN LINE WATER RETICULATION)

KERJA PENGHANTARAN PAIP MSCL KE TAPAK. TARGET SIAP 50%.

KERJA PENGOREKAN PAIP. TARGET SIAP 10%.

KERJA PEMASANGAN PAIP MSCL. TARGET SIAP 10%.

 

(KERJA SEWERAGE RETICULATION)

KERJA PENGHANTARAN PAIP SEWERAGE KE TAPAK. TARGET SIAP 100%.

KERJA PENGOREKAN DAN PEMASANGAN PAIP SEWERAGE. TARGET SIAP 20%.

 

(KERJA SEWERAGE TREATMENT PLANT)

KERJA MEMBUAT PERMOHONAN KEPADA MAJAARI SERVICES S/B. TARGET SIAP 100%.

KERJA PERSEDIAAN MEMBINA STP. TARGET SIAP 100%.