Laporan Bulan Ini


STATUS PEMANTAUAN PROJEK (KERJA FIZIKAL DI TAPAK)

 

BANGUNAN UTAMA

KERJA PEMASANGAN PAIP UNTUK ANTI TERMITE DI ZON 2 TELAH DISIAPKAN KESEMUANYA PADA 26.10.2015.

 

KERJA M&E UNDERGROUND SERVICES

KERJA-KERJA PEMASANGAN PAIP UNTUK M&E UNDERGROUND SERVICES UNTUK ZON 2 TELAH DISIAPKAN KESEMUANYA PADA 20.10.2015.

 

PAPAK LANTAI TANAH

SIAP KONKRIT KESEMUA PAPAK LANTAI TANAH KECUALI KAWASAN CATERING (75%)

 

TIANG

ZON 1, AKTIVITI: KONKRIT 106 NOS DARIPADA KESELURUHAN 122 NOS (87%)

ZON 2, AKTIVITI: KONKRIT 60 NOS DARIPADA KESELURUHAN 90 NOS (67%)

ZON 3, AKTIVITI: KONKRIT 66 NOS DARIPADA KESELURUHAN 78 NOS (85%)

 

CORBEL (LEVEL 2)

ZON 1, AKTIVITI: KONKRIT 30 NOS DARIPADA JUMLAH KESELURUHAN 43 NOS (70%)

ZON 2, AKTIVITI: KONKRIT 30 NOS DARIPADA JUMLAH KESELURUHAN 46 NOS (65%)

ZON 1, AKTIVITI: KONKRIT KESEMUA 20 NOS DARIPADA JUMLAH KESELURUHAN 21 NOS (97%)

STATUS PEMANTAUAN PROJEK (KERJA FIZIKAL DI TAPAK)

BANGUNAN UTAMA

KERJA ANTI TERMITE
KERJA PEMASANGAN PAIP UNTUK ANTI TERMITE DI ZON 2 TELAH DISIAPKAN KESEMUANYA PADA 26.10.2015.

KERJA M&E UNDERGROUND SERVICES
KERJA-KERJA PEMASANGAN PAIP UNTUK M&E UNDERGROUND SERVICES UNTUK ZON 2 TELAH DISIAPKAN KESEMUANYA PADA 20.10.2015.

 

PAPAK LANTAI TANAH

ZON 2, AKTIVITI : SIAP KONKRIT KESEMUA PAPAK LANTAI TANAH KECUALI KAWASAN CATERING (75%)

 

TIANG

ZON 1, AKTIVITI : KONKRIT 106 NOS DARIPADA KESELURUHAN 122 NOS (87%)

ZON 2, AKTIVITI : KONKRIT 60 NOS DARIPADA KESELURUHAN 90 NOS (67%)

ZON 3, AKTIVITI : KONKRIT 66 NOS DARIPADA KESELURUHAN 78 NOS (85%)

 

CORBEL (LEVEL 2)

ZON 1, AKTIVITI : KONKRIT 30 NOS DARIPADA JUMLAH KESELURUHAN 43 NOS (70%)

ZON 2, AKTIVITI : KONKRIT 30 NOS DARIPADA JUMLAH KESELURUHAN 46 NOS (65%)

ZON 3, AKTIVITI : KONKRIT KESEMUA 20 NOS DARIPADA JUMLAH KESELURUHAN 21 NOS (97%)

 

NIB/ BEAM (LEVEL 2)

ZON 1, AKTIVITI : KONKRIT DI GRIDLINE 3-5/H-N, 3/N-P, 6-8/K-Q & 9/M-R.

ZON 2, AKTIVITI : KONKRIT DI GRIDLINE 10-11/E-J, 12/F-J & H1/10-12.

zon 3, AKTIVITI : KONKRIT DI GRIDLINE 10-12/M-N, 11-12/N-Q & 10-12/Q-R.

 

IBS BEAM (LEVEL 2)

ZON 1, AKTIVITI : PEMASANGAN IBS BEAM SEBANYAK 23 NOS DARIPADA JUMLAH KESELURUHAN 39 NOS. (59%)

ZON 2, AKTIVITI : PEMASANGAN IBS BEAM SEBANYAK 25 NOS DARIPADA JUMLAH KESELURUHAN 44 NOS. (57%)

ZON 3, AKTIVITI : PEMASANGAN IBS BEAM SEBANYAK 17 NOS DARIPADA JUMLAH KESELURUHAN 18 NOS. (94%)

 

HOLLOW CORE SLAB (LEVEL 2)

ZON 1, AKTIVITI : PEMASANGAN HOLLOW CORE SLAB DI GRIDLINE H-H1/3-4 & H1-M/3-5.

ZON 3, AKTIVITI : PEMASANGAN HOLLOW CORE SLAB DI GRID LINE M-N/9-12, 11-12/N-Q & Q-R/9-12.

 

PAPAK LANTAI CAST IN-SITU (LEVEL 2)

ZON 3, AKTIVITI : KERJA-KERJA KONKRIT TELAH DILAKUKAN DI GRIDLINE 9-11/ N-Q & 9-12/ R (CURVE).

 

HOUSEMEN QUARTERS DAN NURSES HOSTEL

KERJA TETOPI CERUCUK UNTUK NURSES HOSTEL
SEHINGGA 11.10.2015

ZON NURSES HOSTEL (33 Nos), KONKRIT TETOPI CERUCUK (33 Nos) AND PERATUS TETOPI CERUCUK YANG SIAP DIKONKRIT (100 %)

 

HOUSEMEN QUARTERS DAN NURSES HOSTEL

HOUSEMEN QUARTERS

(RASUK TANAH)
KERJA-KERJA KONKRIT KESEMUA RASUK TANAH SIAP DILAKUKAN PADA 05.10.2015.

(PAIP SANITARY)
KERJA-KERJA PEMASANGAN PAIP SANITARY SIAP DILAKUKAN.

(PAPAK LANTAI TANAH)
KERJA-KERJA MENGHAMPARKAN BESI BRC SEDANG DILAKUKAN.

 

NURSES HOSTEL

(RASUK TANAH)
KERJA-KERJA KONKRIT RASUK TANAH DI GRID LINE D-J/ 1-6 & F-H/ 6-7.

KERJA-KERJA PEMASANGAN KOTAK BENTUK DAN BESI TETULANG MASIH SEDANG DIJALANKAN.

 

BLOK M&E

KERJA-KERJA TETOPI CERUCUK
SEHINGGA 11.10.2015

BANGUNAN BLOK M&E (63 nos, PENGOREKAN (63 nos), KONKRIT TETOPI CERUCUK (63 nos) DAN PERATUS TETOPI CERUCUK YANG SIAP DIKONKRIT (100 %)

KERJA-KERJA STUMP
SEHINGGA 25.10.2015

BANGUNAN BLOK M&E (63 nos), KONKRIT STUMP ( 63 nos) DAN PERATUS STUMP YANG SIAP DIKONKRIT (100%)

 

BALAI PELAWAT

PAIP SANITARY
KERJA-KERJA PEMASANGAN PAIP SANITARY UNTUK BALAI PELAWAT TELAH DILAKUKAN.

BESI
KERJA-KERJA PEMASANGAN BESI BAGI ASAS RAKIT UNTUK BALAI PELAWAT TELAH DILAKUKAN.

 

BLOK TADIKA

PAIP SANITARY
KERJA-KERJA PEMASANGAN PAIP SANITARY UNTUK BLOK TADIKA TELAH DILAKUKAN.

 

SEWERAGE

KERJA PENGOREKKAN TANAH BAGI MAINHOLE 14, MAINHOLE 13 & MAINHOLE 12.

KERJA PEMASANGAN MAINHOLE 14, MAINHOLE 13 & MAINHOLE 12

KERJA PEMASANGAN PAIP VCP DI ANTARA MAINHOLE 14 KE MAINHOLE 13 DAN DARI MAINHOLE 13 KE MAINHOLE 12.

Perancangan Bulan Hadapan


KERJA FIZIKAL

KERJA PAPAK LANTAI TANAH

BANGUNAN UTAMA
ZON 2 DAN TARGET SIAP BAGI KERJA PAPAK LANTAI TANAH (75-100%)

 

TIANG

PENYIAPAN BAKI KERJA-KERJA PEMBINAAN TIANG UNTUK ZON 1 (TARGET SIAP DARI 87%-100%).

PENYIAPAN KERJA-KERJA PEMBINAAN TIANG BAGI ZON 2 (TARGET SIAP DARI 67%-100%).

PENYIAPAN BAKI KERJA-KERJA PEMBINAAN TIANG UNTUK ZON 3 (TARGET SIAP DARI 85%-100%).

 

CORBEL & NIB BEAM LEVEL 2

PENYIAPAN BAKI KERJA PEMBINAAN CORBEL & NIB BEAM LEVEL 2 UNTUK ZON 1, ZON 2 DAN ZON 3 (TARGET SIAP 100%).

 

IBS BEAM LEVEL 2

PENYIAPAN BAKI KERJA PEMASANGAN IBS BEAM BAGI LEVEL 2 UNTUK ZON 1, ZON 2 DAN ZON 3 (TARGET SIAP 100%).

 

BEAM CAST IN SITU LEVEL 2

PENYIAPAN BAKI KERJA PEMBINAAN BEAM CAST IN SITU BAGI LEVEL 2 UNTUK ZON 1, ZON 2 DAN ZON 3 (TARGET SIAP 100%).

 

HOLLOW CORE SLAB LEVEL 2

PENYIAPAN BAKI KERJA PEMASANGAN HOLLOW CORE SLAB LEVEL 2 UNTUK ZON 1 & ZON 3 (TARGET SIAP 100%).

KERJA PEMASANGAN HOLLOW CORE SLAB LEVEL 2 UNTUK ZON 2 AKAN DIMULAKAN.

 

SLAB CAST IN-SITU LEVEL 2

PENYIAPAN BAKI KERJA PEMBINAAN SLAB CAST IN-SITU LEVEL 2 UNTUK ZON 3 (TARGET SIAP 100%).

KERJA PEMBINAAN SLAB CAST IN-SITU LEVEL 2 UNTUK ZON 1 & ZON 2 AKAN DIMULAKAN.

 

TIANG LEVEL 2

KERJA-KERJA PEMBINAAN TIANG LEVEL 2 UNTUK ZON 1 DAN ZON 3 (TARGET SIAP 50%).

 

NURSES HOSTEL & HOUSEMEN QUARTERS

RASUK TANAH

PENYIAPAN BAKI KERJA PEMBINAAN RASUK TANAH UNTUK NURSES HOSTEL (TARGET SIAP DARI 30%-100%).

KERJA-KERJA PEMBINAAN PAPAK LANTAI TANAH UNTUK HOUSEMEN QUARTERS (TARGET SIAP 100%).

PAPAK LANTAI TANAH

KERJA-KERJA PEMBINAAN PAPAK LANTAI TANAH UNTUK NURSES HOSTEL (TARGET SIAP 100%).

KERJA-KERJA PEMBINAAN PAPAK LANTAI TANAH UNTUK HOUSEMEN QUARTERS (TARGET SIAP 100%).

 

BLOK M&E

RASUK TANAH

KERJA-KERJA PEMBINAAN RASUK TANAH UNTUK BLOK M&E (TARGET SIAP 50%).

 

BLOK BALAI PELAWAT & TADIKA

KERJA ASAS TAPAK

KERJA-KERJA PEMBINAAN ASAS TAPAK BLOK BALAI PELAWAT. TARGET SIAP DARI 75%-100%.

KERJA-KERJA PEMBINAAN ASAS TAPAK BLOK TADIKA. TARGET SIAP DARI 30%-100%.

 

KERJA FIZIKAL (INFRA)

KERJA AC/DC

KERJA MENGHAMPAR LAPISAN PREMIX BINDER COARSE. TARGET SIAP 100%.

A LINK BRIDGE

KERJA PILING. TARGET SIAP 100%

KERJA PENGHANTARAN BOX CULVERT KE TAPAK. TARGET SIAP 100%.

KERJA PEMASANGAN BOX CULVERT. TARGET SIAP 50%.

 

KERJA MAIN LINE WATER RETICULATION

KERJA PENGHANTARAN PAIP MSCL KE TAPAK. TARGET SIAP 50%.

KERJA PENGOREKAN PAIP. TARGET SIAP 10%.

KERJA PEMASANGAN PAIP MSCL. TARGET SIAP 10%.

 

KERJA SEWERAGE RETICULATION

KERJA PENGHANTARAN PAIP SEWERAGE KE TAPAK. TARGET SIAP 100%.

KERJA PENGOREKAN DAN PEMASANGAN PAIP SEWERAGE. TARGET SIAP 20%.

 

KERJA SEWERAGE TREATMENT PLANT

KERJA MEMBUAT PERMOHONAN KEPADA MAJAARI SERVICES S/B. TARGET SIAP 100%.

KERJA PERSEDIAAN MEMBINA STP. TARGET SIAP 100%.

 