Laporan Bulan Ini


KERJA- KERJA AWALAN

 

PEJABAT PENGARAH PROJEK (JKR)

BILIK MESYUARAT TAPAK

PEJABAT TAPAK KONTRAKTOR

PAPAN TANDA PROJEK

PENYAMBUNGAN BEKALAN AIR SEMENTARA

PENYAMBUNGAN BEKALAN ELEKTRIK SEMENTARA

PENYAMBUNGAN TALIAN TELEFON & INTERNET SEMENTARA

PEMBINAAN 1 UNIT WASH TROUGH

LALUAN JALAN MASUK SEMENTARA

 

MAKLUMAT KONTRAK

NO KONTRAK : JKR/IP/CKUB/65/2014
JUMLAH KONTRAK : RM 286,000,000.00
TARIKH MILIK TAPAK : 20 MEI 2014
TEMPOH KONTRAK : 36 BULAN
TEMPOH KECACATAN : 24 BULAN

CONTRACTOR’S ALL RISK INSURANCE

NO POLISI : CEC-12718018-C1
TARIKH TAMAT : 9/12/2019
JUMLAH INSURAN : RM 286,000,000.00

 

KEY FACILITIES

268 BEDS
EMERGENCY DEPARTMENT
DAYCARE FACILITIES
DIALYSIS CENTRE
SPECIALIST CLINICS
8 NOS OPERATION THEATRES
PREGNANCY ASSESSMENT CENTRE (PAC)
INTENSIVE CARE UNIT (ICU)
PEDIATRIC INTENSIVE CARE UNIT (PICU)
NEO-NATAL INTENSIVE CARE UNIT (NICU)
SPECIAL CARE NURSERY (SCN)
CORONARY CARE UNIT (CCU/CRW)
HIGH DEPENDENCY WARD (HDW)
IMAGING DEPARTMENT
PHARMACY DEPARTMENT
PATHOLOGY DEPARTMENT
REHABILITATION CENTER
CENTRAL STERILE SUPPLY DEPARTMENT (CSSD)

 

PROGRESS PEMBINAAN

TARIKH MASUK TAPAK ADALAH 20 MEI 2014.

KERJA MEMBINA PAPAN TANDA PROJEK

MEMBINA PEJABAT TAPAK & PEJABAT PENGARAH PROJEK

PENYAMBUNGAN BEKALAN AIR SEMENTARA

KERJA PENYIASATAN TAPAK 9 (BORE HOLE) LUBANG DILAKUKAN DI TAPAK

 

MASTERPLANNING / OVERALL LAYOUT

DATE|16th April 2014     ACTION|Mesyuarat Verifikasi Rekabentuk Konsep     STATUS|Done
DATE|6th May 2014      ACTION|Mesyuarat Memuktamadkan Rekabentuk Konsep     STATUS|Done
DATE|9th May 2014      ACTION|Masterplan Drawing submitted for KKM’s endorsement      STATUS|Done
DATE|26th May 2014      ACTION|Masterplan Drawing endorsed by KKM      STATUS|Done

Submit to Town Planner to proceed with DO submission

 

INTER-DEPARTMENTAL LAYOUT / LOADED DRAWINGS

DATE|10th June 2014      ACTION|Medical Planner to submit loaded drawings for KKM’s review      STATUS|Done
DATE|18th July 2014      ACTION|Loaded Drawings / SOA approved by KKM      STATUS|N/A
DATE|28th & 29th July 2014      ACTION|Hari Raya Aidilfitri      STATUS| N/A
DATE|11th August to 5th Sept 2014(3 weeks)      ACTION|Room Data Interaction      STATUS|N/A

 

DEVELOPMENT ORDER SUBMISSION

DATE|21st May 2014       ACTION|Preparation of DO Submission (Drawings & LCP)   STATUS|Done
DATE|5th June 2014       ACTION|Pra-Rundingan with JPBD Kelantan     STATUS|Done
DATE|16th June 2014      ACTION|Submission DO to JPBD      STATUS|Done
DATE|23rd June 2014     ACTION|Mesyuarat Jawatankuasa Teknikal for DO Approval     STATUS|N/a
DATE|14th July 2014       ACTION|Final submission for JPBD endorsement     STATUS|N/a
DATE|25th July 2014      ACTION|DO Approval      STATUS|N/a

 

BUILDING PLAN SUBMISSION

DATE|5th August 2014      ACTION|Preparation of Building Plan Submission Drawings      STATUS|N/a
DATE|3rd September 2014      ACTION|Building Plan Submission      STATUS|N/a
DATE|3rd December 2014      ACTION|Building Plan Approval obtained      STATUS|N/a

 

RINGKASAN EKSEKUTIF

KEMAJUAN FIZIKAL

KUMULATIF PERANCANGAN KERJA : 0 %
STATUS KERJA SEBENAR : 0%
PERBEZAAN (+/-) : 0%
PERBEZAAN (HARI) : -

KEMAJUAN KEWANGAN
KUMULATIF PERANCANGAN KERJA : 0.5 %
STATUS KERJA SEBENAR : 0.65 %
PERBEZAAN (+/-) : +0.15 %

 

STATUS KEMAJUAN KERJA

PROGRESS PEMBINAAN

TARIKH MASUK TAPAK ADALAH 20 MEI 2014.
KERJA MEMBINA PAPAN TANDA PROJEK
MEMBINA PEJABAT TAPAK & PEJABAT PENGARAH PROJEK
PENYAMBUNGAN BEKALAN AIR SEMENTARA
KERJA PENYIASATAN TAPAK 9 (BORE HOLE) LUBANG DILAKUKAN DI TAPAK