Laporan Bulan Ini


STATUS PEMANTAUAN PROJEK (KERJA FIZIKAL DI TAPAK)

BANGUNAN UTAMA

1 - BANGUNAN UTAMA

 

2 -

 

PRECAST/IN-SITU

3 - PRE CAST IN SITU

 

MAIN BUILDING (LEVEL 2) COLUMN

4 - MAIN BUILDING LEVEL 2 COLUMN

 

MAIN BUILDING (LEVEL 3) COLUMN

5 - MAIN BUILDING LEVEL 3

 

MAIN BUILDING (LEVEL 3) PRECAST/IN-SITU

6 - PRECAST MAIN BUILDING LEVEL 3 IN SITU

 

MAIN BUILDING LEVEL 2

7 - MAIN BUILDING LEVEL 2

 

MAIN BUILDING LEVEL 3

8 - MAIN BUILDING LEVEL 3

 

MAIN BUILDING (LEVEL 3) PRECAST/ IN-SITU

9 - MAIN BUILDING LEVEL 3 PRE CAST IN SITU

 

MAIN BUILDING (LEVEL 3) COLUMN

10 - MAIN BUILDING LEVEL 3 COLUMN

 

MAIN BUILDING LEVEL 3 CONCRETE CORBEL

11 - MAIN BUILDING LEVEL 3 CONCRETE CORBEL

 

MAIN BUILDING LEVEL 3 COLUMN

10 - MAIN BUILDING LEVEL 3 COLUMN

 

MAIN BUILDING (LEVEL 4) CORBEL

14 - MAIN BUILDING LEVEL 4 CORBEL

 

MAIN BUILDING (LEVEL 4) PRECAST/IN-SITU

15 - MAIN BUILDING LEVEL 4 CAST IN SITU

 

MAIN BUILDING (LEVEL 1)

16 -

 

17 -

 

MAIN BUILDING (LEVEL 2) CORBEL

18 -

 

RINGKASAN KEMAJUAN KERJA FIZIKAL

19 -

 

20 -

 

HOUSEMEN QUARTERS (LEVEL 2) PRECAST STAIRCASE

21 - HOUSEMEN QUARTERS LEVEL 2 PRECAST STAIRCASE

 

PRECAST COLUMN 30 NOS INSTALLED

22 - PRECAST COLUMN 30 NOS INSTALLED

 

HOUSEMEN QUARTERS (LEVEL 3) PRECAST BEAM

23 - HOUSEMEN QUARTERS LEVEL 3 PRECAST BEAM

 

HOUSEMEN QUATERS (LEVEL 3)

24 - HOUSEMEN QUATERS LEVEL 3

 

HOUSEMEN QUARTERS (LEVEL 3) PRECAST COLUMN

25 - HOUSEMEN QUARTERS LEVEL 3 PRECAST COLUMN

&nbsp,

HOUSEMEN QUARTERS (LEVEL 4) PRECAST BEAM

26 - HOUSEMEN QUARTERS LEVEL 4 PRECAST BEAM

 

NURSE QUARTERS (LEVEL 1) GROUND SLAB

27 - NURSE QUARTERS  LEVEL 1 GROUND SLAB

 

NURSES HOSTEL (LEVEL 1)

28 - NURSES HOSTEL LEVEL 1

 

NURSES HOSTEL (LEVEL 2) PRECAST BEAM

29 - NURSES HOSTEL LEVEL 2 PRECAST BEAM

 

NURSES HOSTEL (LEVEL 2)

30 - NURSES HOSTEL LEVEL 2

 

NURSES HOSTEL (LEVEL 2) PRECAST COLUMN

31 - NURSES HOSTEL LEVEL 2 PRECAST COLUMN

 

NURSES HOSTEL (LEVEL 3) PRECAST BEAM

32 - NURSES HOSTEL LEVEL 3 PRECAST BEAM

 

33 -

 

M&E BLOCK (LEVEL 1) GROUND BEAM

34 - M&E BLOCK LEVEL 1 GROUND BEAM

 

M&E BLOCK (LEVEL 1) CROUND SLAB

35 - M&E BLOCK LEVEL 1 CROUND SLAB

 

36 -

 

VISITOR HALL (LEVEL 1) COLUMN

37 - VISITOR HALL LEVEL 1 COLUMN

 

VISITOR HALL (LEVEL 2) ROOF BEAM

38 - VISITOR HALL LEVEL 2 ROOF BEAM

 

TADIKA

39 - TADIKA

 

KINDERGARTEN CRECHE (LEVEL 1) COLUMN

40 - KINDERGARTEN CRECHE LEVEL 1 COLUMN

 

KINDERGARTEN CRECHE (LEVEL 1) ROOF BEAM

41 - KINDERGARTEN CRECHE LEVEL 1 ROOF BEAM

 

KERJA FIZIKAL (INFRA)

KERJA AC/DC
KERJA MENGHAMPAR LAPISAN PREMIX BINDER COURSE TELAH DILAKUKAN PADA 26.12.2016

KERJA TWIN BOX CULVERT (LALUAN KECEMASAN & LALUAN UTAMA)
KERJA KERJA PENANAMAN PILOT PILE BERSAIZ 200mmx200mm SEBANYAK 10 NOS SETIAP LALUAN TELAH DILAKUKAN PADA 21.01.2016

 

BOX CULVERT PILING EMERGENCY ENTRANCE

44 - BOX CULVERT PILING EMERGENCY ENTRANCE

 

BOX CULVERT PILING MAIN ENTRANCE

45 - BOX CULVERT PILING MAIN ENTRANCE

 

KERJA FIZIKAL INFRA SEWERGE

46 - KERJA FIZIKAL INFRA SEWERGE

 