Laporan Bulan Ini


STATUS PEMANTAUAN PROJEK (KERJA FIZIKAL DI TAPAK)

PELAN LANTAI BANGUNAN UTAMA

1 Pelan lantai bangunan Utama

 

2 Bangunan Utama

 

3 Bangunan Utama

 

ZON 1

4 ZON 1

 

MAIN BUILDING (CORBEL) WORK PROGRESS

5 Zon 1

 

MAIN BUILDING (LEVEL 3) PRECAST/ IN-SITU WORK PROGRESS

6 Zone 1

 

MAIN BUILDING (COLUMN) WORK PROGRESS

7 Zone 1

 

PEMANDANGAN KERJA-KERJA PEMBINAAN ARAS 3 DAN 4 DI ZONE 1

8 Pemandangan kerja kerja pembinaan aras 3 dan 4 di Zon 1

 

KERJA-KERJA PENGHAMPARAN BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 3 DI ZON 1

10 KERJA-KERJA PENGHAMPARAN BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 3 DI ZON 1

 

KERJA-KERJA PENGHAMPARAN BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 3 DI ZON 1

11 KERJA-KERJA PENGHAMPARAN BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 3 DI ZON 1

 

NIB BEAM ARAS 3 DAN KERJA KERJA MEMASANG BESI TETULANG BAGI ZON 1

12 NIB  BEAM ARAS 3 DAN KERJA KERJA MEMASANG BESI TETULANG BAGI I ZON 1

 

NIB BEAM ARAS 3 DAN KERJA KERJA MEMASANG BESI TETULANG BAGI ZON 1

13 NIB  BEAM ARAS 3 DAN KERJA KERJA MEMASANG BESI TETULANG BAGI I ZON 1

 

KERJA KERJA MEMASANG KOTAK BENTUK BAGI BEAM DAN SLAB ARAS 4 DI ZON 1

14 KERJA KERJA MEMASANG KOTAK BENTUK BAGI BEAM DAN SLAB ARAS 4 DI ZON 1

 

KERJA KERJA MEMASANG KOTAK BENTUK BAGI BEAM DAN SLAB ARAS 4 DI ZON 1

15 KERJA KERJA MEMASANG KOTAK BENTUK BAGI BEAM DAN SLAB ARAS 4 DI ZON 1

 

ZON 2

16 ZONE 2

 

MAIN BUILDING ZONE 2

17 Main Building ZONE 1

 

PRE CAST IN SITU AT ZONE 2

18 PRE CAST IN SITU AT ZONE 2

 

PEMANDANGAN KERJA KERJA PEMBINAAN ARAS 4 DI ZON 2

19 PEMANDANGAN KERJA KERJA PEMBINAAN ARAS 4 DI ZON 2

 

20 PEMANDANGAN KERJA KERJA PEMBINAAN ARAS 4 DI ZON 2

20 PEMANDANGAN KERJA KERJA PEMBINAAN ARAS 4 DI ZON 2

 

KERJA KERJA PEMBINAAN NIB BEAM ARAS 4 DI ZON 2

21 KERJA KERJA PEMBINAAN NIB  BEAM ARAS 4 DI ZON 2

 

KERJA KERJA PEMBINAAN NIB BEAM ARAS 4 DI ZON 2

22 KERJA KERJA PEMBINAAN NIB  BEAM ARAS 4 DI ZON 2

 

ZONE 3

23 ZONE 3

 

PEMANDANGAN KERJA-KERJA PEMBINAAN ARAS 4 DI ZON 3

24 PEMANDANGAN KERJA-KERJA PEMBINAAN ARAS 4 DI ZON 3

 

PEMANDANGAN KERJA-KERJA PEMBINAAN ARAS 4 DI ZON 3

25 PEMANDANGAN KERJA-KERJA PEMBINAAN ARAS 4 DI ZON 3

 

KERJA-KERJA MEMASANG BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 4 DI ZON 3

26 KERJA-KERJA MEMASANG BESI BRC DI ATAS HOLLOW CORE SLAB ARAS 4 DI ZON 3

 

KERJA-KERJA MEMASANG BESI TETULANG DAN KOTAK BENTUK BAGI NIB BEAM ARAS 4 DI ZON 3

27 KERJA-KERJA MEMASANG BESI TETULANG DAN KOTAK BENTUK BAGI NIB BEAM ARAS 4 DI ZON 3

 

KERJA-KERJA MENGIKAT BATA ARAS 1 DI ZON 3

28 KERJA-KERJA MENGIKAT BATA ARAS 1 DI ZON 3

 

KERJA-KERJA MENGIKAT BATA ARAS 1 DI ZON 3

29 KERJA-KERJA MENGIKAT BATA ARAS 1 DI ZON 3

 

KERJA KERJA MENGIKAT BATA ARAS 1 DI ZON 3

30 KERJA KERJA MENGIKAT BATA ARAS 1 DI ZON 3

 

KERJA KERJA MENGIKAT BATA ARAS 1 DI ZON 3

31 KERJA KERJA MENGIKAT BATA ARAS 1 DI ZON 3

 

CATERING

32 CATERING

 

CATERING DEPARTMENT LEVEL 2

33 CATERING DEPARTMENT LEVEL 2

 

KERJA-KERJA MEMASANG PRECAST BEAM (PERIMETER) DI CATERING DEPARTMENT

34 KERJA-KERJA MEMASANG PRECAST BEAM (PERIMETER) DI CATERING DEPARTMENT

 

HOUSEMEN AND NURSES HOSTEL

36 HOUSEMEN AND NURSES HOSTEL

 

HOUSEMEN AND NURSES HOSTEL

37 HOUSEMEN AND NURSES HOSTEL

 

HOUSEMEN QUARTERS

38 HOUSEMEN QUARTERS

 

HOUSMEN QUARTERS

39 HOUSMEN QUARTERS

 

HOUSEMEN QUARTERS PRECAST COLUMN

40 HOUSEMEN QUARTERS PRECAST COLUMN

 

HOUSEMEN QUARTERS PRECAST ARAS BUMBUNG

41 HOUSEMEN QUARTERS PRECAST ARAS BUMBUNG

 

PEMANDANGAN PEMBINAAN YANG TELAH SIAP BAGI KERJA-KERJA STRUKTUR DI HOUSEMEN QUARTER

42 PEMANDANGAN PEMBINAAN YANG TELAH SIAP BAGI KERJA-KERJA STRUKTUR DI HOUSEMEN QUARTERS

 

KERJA-KERJA MENGIKAT BATA ARAS 1 DIMULAKAN DI HOUSEMEN QUARTERS

43 KERJA-KERJA MENGIKAT BATA ARAS 1 DIMULAKAN DI HOUSEMEN QUARTERS

 

KERJA KERJA MENGIKAT BATA ARAS 1 DIMULAKAN DI HOUSEMEN QUARTERS

44 KERJA KERJA MENGIKAT BATA ARAS 1 DIMULAKAN DI HOUSEMEN QUARTERS

 

NURSES HOSTEL

45 NURSES HOSTEL

 

NURSES HOSTEL PRE CAST IN SITU

46 NURSES HOSTEL PRE CAST IN SITU

 

NURSES HOSTEL INSTALLED PRECAST COLUMN

47 NURSES HOSTEL INSTALLED PRECAST COLUMN

 

NURSES HOSTEL INSTALLED PRECAST BEAM

48 NURSES HOSTEL INSTALLED PRECAST BEAM

 

KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

49 KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

 

KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

50 KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

 

KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

51 KERJA KERJA MEMASANG IBS BEAM ARAS BUMBUNG DI NURSES HOSTEL

 

BLOCK M&E

52 BLOCK M&E

 

BLOCK M&E

53 BLOCK M&E

 

M&E BLOCK (LEVEL 1- LEVEL INTERMEDIATE COLUMN)

54 BLOCK M&E

 

M&E BLOCK (LEVEL INT) BEAM WORK IN PROGRESS

55 BLOCK M&E

 

M&E BLOCK (LEVEL 2) COLUMN WORK IN PROGRESS

56 BLOCK M&E

 

PEMANDANGAN KERJA KERJA PEMBINAAN TIANG & RASUK INTERMEDIATE DI BLOK M&E

57 PEMANDANGAN KERJA KERJA PEMBINAAN TIANG & RASUK INTERMEDIATE DI BLOK M&E

 

PEMANDANGAN KERJA-KERJA PEMBINAAN TIANG & RASUK INTERMEDIATE DI BLOK M&E

58 PEMANDANGAN KERJA-KERJA PEMBINAAN TIANG & RASUK INTERMEDIATE DI BLOK M&E

 

STATUS KEMAJUAN KERJA KERJA INFRA

63 STATUS KEMAJUAN KERJA KERJA INFRA

 

WASTE MANAGEMENT

59 WASTE MANAGEMENT

 

PEMANDANGAN DI BLOK WASTE MANAGEMENT

60 PEMANDANGAN DI BLOK WASTE MANAGEMENT

 

KERJA-KERJA PENYEMBURAN ANTI TERMITE DI BLOK WASTE MANAGEMENT

61 KERJA-KERJA PENYEMBURAN ANTI TERMITE DI BLOK WASTE MANAGEMENT

 

KERJA-KERJA PENYEMBURAN ANTI TERMITE DI BLOK WASTE MANAGEMENT

62 KERJA-KERJA PENYEMBURAN ANTI TERMITE DI BLOK WASTE MANAGEMENT

 

STATUS KEMAJUAN KERJA KERJA INFRA

63 STATUS KEMAJUAN KERJA KERJA INFRA

 

KERJA KERJA INFRA

64 KERJA KERJA INFRA

 

KERJA-KERJA PENGOREKAN BAGI PEMBINAAN MANHOLE & SEWERLINE

65 KERJA-KERJA PENGOREKAN BAGI PEMBINAAN MANHOLE & SEWERLINE

 

KERJA-KERJA PENGOREKAN BAGI PEMBINAAN MANHOLE & SEWERLINE

66 KERJA-KERJA PENGOREKAN BAGI PEMBINAAN MANHOLE & SEWERLINE